Audit Report
This report reflects the findings of the Office of Inspector General at the time that the audit report was issued. More current information may be available as a result of the resolution of this audit by the Department of Labor program agency and the auditee. For further information concerning the resolution of this report's findings, please contact the program agency.
Report Number: Final Report No. 18-98-004-04-370
Issue Date: January 27, 1998
During the contract closeout process for operation of Job Corps Centers in McKinney, Texas and Guthrie, Oklahoma, The Wackenhut Corporation, Inc. (Wackenhut) determined that a significant cost overrun occurred at the Guthrie Center and a lesser overrun at the McKinney Center. Wackenhut claimed the overruns were due to an unusual set of circumstances over which it had little or no control and, therefore, should be paid the entire amount of the cost overruns plus unpaid contract amounts for which Job Corps had withheld final payment.
The Job Corps requested that the OIG review the Wackenhut claim to determine:
(2) the circumstances under which the expenses were incurred.
The OIG determined that most of the costs Wackenhut had claimed and Job Corps had not yet paid (both costs "within the contract" and overruns) were legitimate Job Corps expenses. The OIG also determined there were, in fact, unusual circumstances which complicated and aggravated the contract closeout process and contributed to the cost overruns. There were conditions within Wackenhut which contributed to the lax oversight of accrued expenses. Further, there were conditions external to Wackenhut, beyond their control, which contributed to the operational overruns.
On December 17, 1997, primarily as a result of the OIG's review, the Job Corps and Wackenhut entered into a Settlement Agreement. The terms of the agreement included Job Corps reimbursing Wackenhut a fair amount on its unpaid claims for both contracts, determined to be $2.1 million, which saved DOL a total of $582,608 and avoided the costs of subsequent litigation. The total savings is comprised of reductions of $205,992 in the amounts of the two contracts and $376,616 of allowable costs not claimed by Wackenhut, including interest costs to which Wackenhut would otherwise have been entitled under the Prompt Payment Act.